Busy Mission Planned For Crew
HOUSTON, Updated 1:55 p.m. EST October 30, 2000 -- The Expedition One crew members will be busy with a variety of tasks regarding the assembly of the station and the enhancement of their living and working quarters.
Here is a month-by-month overview of their mission:
- November:
- Soyuz launch and docking to ISS
- Zvezda systems activation
- Zvezda outfitting
- Progress resupply ship launch and docking
- Progress unloading
- Experiments
- Space shuttle launch
- December:
- Progress undocking
- Space shuttle docking and U.S. solar arrays installation
- Solar arrays checkout
- Space shuttle undocking
- Spacewalk preparation
- Internal spacewalk to move Zvezda docking probe
- Progress resupply ship launch and docking
- Experiments
- January:
- Solar arrays checkout
- Experiments
- Progress unloading
- Progress undocking
- Space shuttle launch and docking
- U.S. Destiny laboratory installation and activation
- Space shuttle undocking
- Soyuz repositioning from Zvezda to Zarya
- U.S. Destiny laboratory checkouts
- February:
- Progress resupply ship launch and docking
- Progress unloading
- U.S. Destiny laboratory checkouts
- Crew packs for return to Earth
- Space shuttle launch and docking
- Crew handover
- Space shuttle undocking
- Expedition One crew returns to Earth